Brick work calculation in feet
Brick work calculation in feet
1 cum brick work and brick size is (230 x 120 x 75)
1cum Bricks equal to 77 percentage Bricks and 23 percentage mortar
1cum brick=0.77+0.23
So, number of bricks =0.77/(0.23x0.120x0.075) =370 Nos
Mortar Ratio 1:6
1cum wet mortar is equal to dry volume=1.33
so that 0.23 cum wet volume =0.23x1.33=0.31 cum
Ratio is 1:6 =1+6=7
Cement: (1/7)x0.31=0.044/0.035=1.27 Bag (64 kg)
(cement unit weight is 1450=50/1450=0.035)
Sand: (1/7)x0.31x6=0.266 cum=9.38 cft
Mortar Ratio 1:5
1cum wet mortar is equal to dry volume=1.33
so that 0.23 cum wet volume =0.23x1.33=0.31 cum
Ratio is 1:5 =1+5=6
Cement: (1/6)x0.31=0.052/0.035=1.48 Bag (74kg)
(cement unit weight is 1450=50/1450=0.035)
Sand: (1/6)x0.31x5=0.26 cum= 9.18 cft
Mortar Ratio 1:4
1cum wet mortar is equal to dry volume=1.33
so that 0.23 cum wet volume =0.23x1.33=0.31 cum
Ratio is 1:4 =1+4=5
Cement: (1/5)x0.31=0.062/0.035=1.77 Bag (89kg)
(cement unit weight is 1450=50/1450=0.035)
Sand: (1/5)x0.31x4 =0.248 cum= 8.75cft
Mortar Ratio 1:3
1cum wet mortar is equal to dry volume=1.33
so that 0.23 cum wet volume =0.23x1.33=0.31 cum
Ratio is 1:3 =1+3=4
Cement: (1/4)x0.31=0.078/0.035=2.21 Bag (111kg)
(cement unit weight is 1450=50/1450=0.035)
Sand: (1/4)x0.31x3 =0.232 cum= 8.20cft
Conculation
Number of bricks Will be same all ratio only variation cement and sand
Comments
Post a Comment